Sl No Payment amount. Accomplishment Time limit. Remarks
1 1 Lakh 5 cents fenced and developed land will be booked in the name of the buyer NA NA
2 5 Lakh 5 cents fenced and developed land will be registered in the name of the Buyer. 2 weeks Registration expenses is under the scope of the Buyer.
3 3 Lakh Foundation and plinth concreting for 1000SFT house will be completed. 3 weeks Any deviation from original plan will be charged extra.
4 4 Lakh Wall construction till sunshade level and belt and sunshade concreting. 4 weeks NA
5 5 Lakh Completion of ground floor walls and main slab concreting. 4 weeks NA
6 3 Lakh First floor wall construction and sunshade concreting. 4 weeks NA
7 5 Lakh Completion of first wall construction and main slab concreting. 4 weeks NA
8 2 Lakh Wall plastering, Door windows installation, electrifying, plumbing and Tiling work. 4 weeks NA
9 1 Lakh Installation of kitchen cabinet and applying white primer. Handing over of house keys. 2 weeks NA
TOTAL 29 Lakh Double storey, two bed room, 3bathroom facility with spacious balconies. NA NA